The restoration of the trails starts tomorrow. The Asphalt Contractor will start mobilizing North of Coles Crossing tomorrow, Jan 25 in the morning after schools starts.
They will begin by trenching and installing the sleeves for future irrigation and installing base material where we have the new benches going in on the aprons needed.
There will be no open trenches left after crews leave at the end of a day, however the trails being worked on by section will be CLOSED during construction.
Orange construction fencing and signage will be installed and maintained daily at the ingress/egress points on Coles Crossing Dr and at the Tennis Courts.
This project will incur some damage to the landscape around the tennis courts and will have to be restored after completion, so please have patience with construction until complete.
Posted: January 24, 2023 at 3:50 p.m.